Complaint Details:
As pre Allotment Letter 18 Jan 2007
Scheme open – Sept 2006
Expected commencement March 2007
Completion Schedule – 2years after commencement
Tentative cost B-1 cat 14.04 Lakhs
Super/ Covered Area – 900 SQft
Rate per SQft- 1560/- and 1620 for A Type DU
As Per Update dt -28/Feb/2008 AFNHB/ADM/GMB0166
Revised cost – 16.42 lakhs
Super Area – 938 SQft
Rate per SQft 1750 for both A&B cat
Type B DU parking Podium instead of Basement Parking in order to reduce cost of covered parking
Increase in cost per SQft due to increase in Prices of construction Material in general
Percentage increase in Type A category – 8.025%
Percentage increase in Type B category – 12.18%
Final notice for taking over Possession of DU intimation Received vide AFNHB/ADM/GNB0166
Dt- 16/oct/2015 &balance amt paid Rs 2, 60, 291/- on 7/11/2015.
Total amount paid by me – 21, 52, 000 + equalization charges for delayed payments 37, 341/-
i.e. 21, 89, 341/-
Forwarding of clearance and possession letter dt- 19/jan/2016 for collection of Possession Letter and Certificate of Possession form GM Project Office Site.
First Resident Shifter to DU on 12/2/2014
Sdr Sukhwinder singh (Retd) – B-802
Starts as on 21/2/17 Tower Z work completed in Tota;ity but touching up of paint in common area is pending.
Fire Fighte Equipments & Acceories in custody of contractor
Total DU – 54
Handed Over – 37
Balance- 17
As on 1/11/2016
Who have not taken over DU No. of allotties reflected – 31 In Cat A flats only
For Towers A to I, P & Q (Package – 1)
For which DLP is expired on 31/12/2016
For tower K & O Readiness for hand over as on 24/5/16. Rest of Cat B flats not yet ready as per update uploaded on AFNHB Site.
Called up for taking over DU Z-401 and defect list handed over on 07/06/2016 to AFNHB representative till date no intimation received from board about readiness of the DU.
Also refund of the paid up amount sought through mail to AFNHB on 18/8/2016.
There are so many defects that are intimated to board but its near about a year no updates are provided to us. We made so many efforts we personally went to site many times and have handed over defect list to PD after which PD misbehaved with us. And also had a telephonic conversation with AFNHB New Delhi they also misbehaved with us and no satisfactory reply was provided by them. They said “kar lo jo karna hai”.
Its more than 7 years we are waiting for DU as we have paid our hard earned money. And still waiting for the DU. Kindly help us out and take necessary action. Ask Board either to provide refund of the amount paid to AFNHB with interest OR ask them to provide Flat in proper condition + compensation amount for delay of more than 7 years .